DF Ltd v TS Ltd [2021] NZDT 1315 (21 April 2021) [pdf, 233 KB]
...parties also agree that it was necessary to have engineer’s instructions as to the measurements to carry out the job. That is so fundamental to a job of this nature that it may be viewed as a term of the contract. 8. The project engineer sent an email to DF on 20 October 2020. In the body of the email the engineer wrote: “Some information to get you started. Attached is a sketch on how and where I think the chassis joint should be made. This is effectively turning a standard 8...